SaskPower at the GTH

Modernized facilities, greater operational efficiencies, and more collaboration amongst employees are just a few of many perks SaskPower will enjoy when its logistics warehouse complex at the Global Transportation Hub (GTH) is completed.
The Regina Operations and Maintenance Complex (ROMC) sprawls over 145 acres at the GTH with phase one already complete and phase two expected to be completed in early 2026. The ROMC consolidates six of SaskPower’s Regina-area offices to one facility housing service and support operations, including logistics, metering, fleet and distribution and transmission operations.
“The issue for SaskPower properties is that they’re not getting any younger. There is a strong business need for us to be getting out of these old facilities, some of which were built pre-World War II,” explained Scott Campbell, P.Eng., SaskPower’s Director of Properties and Shared Services.
“From a common-sense perspective, there are a lot of benefits that come from pulling all of these different departments together that are spread out across Regina and into one central location. For us, that is the move to the GTH.”

A Campus-Style Complex Built in Two Phases
The project was spread out over several years into two phases. The first phase includes the construction of a logistics warehouse, a building to house SaskPower’s fleet services, a pole yard and outdoor storage spaces. The first phase opened in 2023.
The finished product is to resemble a small university campus with a cluster of buildings housing different departments and several hundred employees on site.
“It’s an opportunity to modernize our facilities and make sure they suit the work we’re doing and facilitate the size of our equipment,” Campbell said.

Why the GTH Location Works
Construction of the new complex at the GTH is strategic to support transport volumes and major roadway connectivity – the TransCanada Highway, the Regina Bypass and Highway 11 are accessible from the GTH – to service all regions of the province.
SaskPower’s aging Regina locations are found in predominantly commercial areas and residential neighbourhoods. With residential and commercial growth in the city, it has become increasingly difficult for larger utility vehicles to efficiently navigate traffic lights, stop signs and school zones.
Thus, a move to a more centralized hub that is specifically designed to allow free-flowing traffic of oversized vehicles was a logical solution.
In addition, by consolidating six locations spread throughout the city, employees can access all materials at one location without travelling from site to site.
“We’re getting by with the facilities we have but centralizing everyone will allow those interactions to be more efficient,” Campbell said. “It’ll be a one-stop shop for employees to gather their equipment and get on the road.
“The GTH is a fantastic location with its large ramps and wider roads that help get our larger vehicles like our bucket trucks with trailers on the road. It allows us to get on the road and to an emergency or to the construction site faster to serve our customers.”
The new site features pull-through bays for larger vehicles to manoeuvre rather than backing in and out in tight quarters; a larger yard to complete pre-assembly of materials; and, more spacing for trucks to be pre-loaded with materials before commuting to job sites.
Built for the Future
Design of the facilities incorporated a long-term vision, making the site adaptable for “future-proofing” 30 or 40 years from now.
“It’s beneficial for us to share space with neighbours that have similar business models,” Campbell said. “There isn’t a rail spur included in our plan right now, but there’s an opportunity to access rail service nearby should we need it in the future.”
More than 500 employees are expected to be based out of the GTH facility once fully complete.